Achieve Success in the PMI PMI-SP Exam: A Detailed PMI Scheduling Professional Guide

Questions 11

John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

Options:
A.

3000

B.

79

C.

80

D.

3160

PMI PMI-SP Premium Access
Questions 12

Which of the following statements best describes an activity in a project?

Options:
A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.

B.

It is the effort needed to complete a work package.

C.

It is the unit of resource utilization needed to complete a project deliverable.

D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Questions 13

The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Options:
A.

Activity list

B.

Milestone list

C.

Activity attributes

D.

Project document updates

Questions 14

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Options:
A.

1.07

B.

0.98

C.

0.89

D.

Ten percent

Questions 15

Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?

Options:
A.

Cost variances and Cost Performance Index

B.

Scope baseline

C.

Performance measurement baseline

D.

Schedule variances, planned value, and the Schedule Performance Index

Questions 16

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:
A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Questions 17

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

Options:
A.

A significant point in the project

B.

A goal of reaching a significant delivery of project benefits by an identified date

C.

An imposed date for the project to reach a given point

D.

The completion of a project activity that is crucial to project completion

Questions 18

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Options:
A.

Procurement document

B.

Contract

C.

Business case

D.

Project statement of work

Questions 19

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Options:
A.

Critical path method

B.

Schedule management plan

C.

Scheduling tool

D.

Critical chain method

Questions 20

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

Options:
A.

-$48,654

B.

13 percent

C.

-$225,000

D.

0.98

Exam Code: PMI-SP
Certification Provider: PMI
Exam Name: PMI Scheduling Professional
Last Update: Jan 24, 2025
Questions: 323