Applying the Pareto rule when prioritizing the Product Backlog means that:
An Agile team expects a velocity of 8. During sprint planning, the stories were estimatedand prioritized in the following order:
Story A_4Story Points
Story B_2Story Points
Story C_3 Story Points
Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?