Questions 11

The ScrumMaster notices repeated friction between two team members in the Daily Scrum meetings. The next step should be to:

Options:
A.

Attempt to resolve the problem directly and immediately during a Daily Scrum meeting.

B.

Schedule a meeting with them after a Daily Scrum meeting to explore and resolve the issue.

C.

Ignore the friction because a self-organizing team must sort out team conflict issues.

D.

Ask for new resources to replace them before the friction undermines the team’s productivity.

PMI PMI-200 Premium Access
Questions 12

Which of the following is critical for the success of distributed Agile teams?

Options:
A.

Cost containment

B.

High volume of communication

C.

Shared knowledge

D.

Culture of collaboration

Questions 13

Information transmission is greatest amongst team members who are working on:

Options:
A.

Individual tasks in the same work area.

B.

The same task through pair programming.

C.

The same group of tasks individually.

D.

Different tasks on the same project.

Questions 14

The best approach to estimate the work on a project when using story points is to have:

Options:
A.

Team members assign estimates by averaging Planning Poker cards.

B.

The most senior team member prepare the estimates.

C.

Two or three senior team members estimate and take the average of their times.

D.

The team work together to agree on estimates in a group setting.

Questions 15

Who is responsible for the “definition of done”?

Options:
A.

The team

B.

The Product Owner

C.

Management

D.

Project manager

Questions 16

A project team estimates that they should complete 30 story points in the current iteration. Partway through the iteration they realize that they will complete 50 story points at their current rate. The team should:

Options:
A.

Shorten the iteration to meet the estimated velocity.

B.

Continue to work with the estimated velocity.

C.

Increase their estimated velocity.

D.

Release members to meet the estimated velocity.

Questions 17

Which of the following drivers is the most important factor in determining the order in which stories will be developed?

Options:
A.

Relative cost

B.

Customer value

C.

Development effort

D.

Dependencies

Questions 18

Team velocity is used to:

Options:
A.

Measure the percentage of features completed.

B.

Judge productivity within the iteration.

C.

Predict schedules for mature teams.

D.

Give feedback on delivered value.

Questions 19

A development team has finished identifying the tasks they will be accountable for during the next sprint. Which of the following tools best provides transparency into the progress throughout the sprint?

Options:
A.

Burndown chart

B.

Gantt chart

C.

Hours expended chart

D.

Management baseline chart

Questions 20

Continuous integration ensures that a product is:

Options:
A.

Ready to ship when all features are complete.

B.

Delivered for testing at the end of each day.

C.

Technologically ready to deploy at any time.

D.

Deployed after final business approvals.