Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Top Tips for Passing the PMI PMI-002 Exam on Your First Try

Questions 16

Risks are accepted when ___________.

Options:

A.

You develop a contingency plan to execute should the risk event occur

B.

You accept the consequences of the risk

C.

You transfer the risk to another party

D.

Both A and B

Buy Now
Questions 17

What impact does a matrix organization have on project team development?

Options:

A.

No impact at all.

B.

It complicates team development.

C.

It simplifies team development.

D.

It hinders team development completely.

Buy Now
Questions 18

A cost-plus-percentage-cost (CPPC) contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?

Options:

A.

$143,000

B.

$142,000

C.

$140,000

D.

$132,000

Buy Now
Questions 19

Make payment to seller is done in _________.

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Buy Now
Questions 20

Which of the following is an example of indirect costs?

Options:

A.

Salaries of corporate executives

B.

Salaries of full-time project staff

C.

Overhead costs

D.

Both A and C

Buy Now
Questions 21

A tight matrix is ___________________.

Options:

A.

A balanced matrix organization

B.

Where all team members are brought together in one location

C.

Where functional managers operate in a dual reporting structure reporting to both their own departments and to the project manager

D.

Both A and c

Buy Now
Questions 22

You are the project manager for a Software Development projects. You are creating a project schedule network diagram for the code development component of the project. This is an example of _________.

Options:

A.

Fragment Network

B.

Precedence Diagramming Method [PDM]

C.

Activity On Node [AON]

D.

Arrow Diagramming Method [ADM]

Buy Now
Questions 23

A technique for resolving conflict in which the parties agree to have a neutral third party hear the dispute and make a decision is called ____________.

Options:

A.

Negotiation

B.

Arbitration

C.

Smoothing

D.

Forcing

Buy Now
Questions 24

Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?

Options:

A.

A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part.

B.

Contingency reserves may be set aside for known unknowns.

C.

Contingency reserves may be set aside for unknown unknowns.

D.

Contingency reserves are normally included in the project's cost and schedule baselines.

Buy Now
Questions 25

All of the following are communication tools EXCEPT ___________.

Options:

A.

Memos

B.

Verbal circulation of a rumour

C.

videos

D.

Inputting data into a spreadsheet

Buy Now
Questions 26

Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?

Options:

A.

CPM

B.

PERT

C.

Schedule simulation

D.

Path convergence method

Buy Now
Questions 27

Collocation can mean _______________.

Options:

A.

All, or almost all, team members are moved to a central physical location for the life of the project.

B.

Active team members may be at different physical locations, but meet on a regular basis.

C.

A war room is established where team members can meet periodically.

D.

Both A and c are correct.

Buy Now
Questions 28

Which of the following is true about the project charter?

Options:

A.

The project charter should be published under the name of a manager external to the project.

B.

The project charter should be published under the project sponsor's name.

C.

The project charter should be published under the name of the project manager.

D.

The project charter should be published under the name of the project champion.

Buy Now
Questions 29

Analogous estimating ____________.

Options:

A.

Uses bottom-up estimating techniques

B.

Uses the actual costs from a previous, similar project

C.

Is synonymous with top-down estimating

D.

Both B and c are correct

Buy Now
Questions 30

The belief that management's high levels of trust, confidence and commitment to workers leads to high levels of motivation and productivity on the part of workers is a part of which motivation theory?

Options:

A.

Theory Y

B.

Theory Z

C.

Theory X

D.

Contingency Theory

Buy Now
Exam Code: PMI-002
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Sep 16, 2024
Questions: 748

PDF + Testing Engine

$159.99
$64

Testing Engine

$119.99
$48

PDF (Q&A)

$99.99
$40