New Year Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Top Tips for Passing the PMI PMI-001 Exam on Your First Try

Questions 221

In which process might a project manager use risk reassessment as a tool and technique?

Options:
A.

Perform Qualitative Risk Analysis

B.

Risk Control

C.

Monitor and Control Project Work

D.

Plan Risk Responses

PMI PMI-001 Premium Access
Questions 222

Which of the following are examples of interactive communication?

Options:
A.

Intranet sites

B.

Voice mails

C.

Video conferences

D.

Press releases

Questions 223

A risk may be graded into different priorities by which process?

Options:
A.

Risk monitoring and controlling

B.

Risk response planning

C.

Qualitative risk analysis

D.

Quantitative risk analysis

Questions 224

What quality control tool graphically represents how various elements of a system interrelate?

Options:
A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Questions 225

Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?

Options:
A.

Estimate Activity Durations

B.

ControlSchedule

C.

Sequence Activities

D.

Develop Schedule

Questions 226

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:
A.

event.

B.

response,

C.

perception.

D.

impact.

Questions 227

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:
A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Questions 228

The Perform Integrated Change Control process occurs in which Process Group?

Options:
A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Questions 229

Which of the following is a tool or technique used in the Determine Budget process?

Options:
A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Questions 230

When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?

Options:
A.

Upper and lower control limits

B.

Upper and lower specification limits

C.

Process mean

D.

Data points

Questions 231

Labor, materials, equipment, and supplies are examples of:

Options:
A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

Questions 232

Perform Integrated Change Control is the process of:

Options:
A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Questions 233

Change requests are an output from which Project Integration Management process?

Options:
A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Questions 234

At the start of a typical project life cycle, costs are:

Options:
A.

low, peak as work is carried out, and drop as the project nears the end.

B.

low, become steady as work is carried out, and increase as the project nears the end.

C.

high, drop as work is carried out, and increase as the project nears the end.

D.

high, become low as work is carried out, and drop as the project nears the end.

Questions 235

What is the minimum a project schedule must include?

Options:
A.

Variance analysis

B.

A planned start date and a planned finish date for each schedule activity

C.

A critical path diagram

D.

Critical chain analysis

Questions 236

When does risk monitoring and control occur?

Options:
A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Questions 237

The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

Options:
A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Questions 238

An output of the Develop Project Team process is:

Options:
A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Questions 239

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:
A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Questions 240

Analogous cost estimating relies on which of the following techniques?

Options:
A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis