A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and
requested a project manager to work with the firm. The PMO declines to assign a project manager and refers
to another department within the company. Which of the following is MOST likely the reason for this?
Which of the following risk strategies prevents a risk from impacting a project?
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
While preparing to plan a project, the project manager meets with the key stakeholders to determine the
flexibility between the project constraints. Which of the following techniques should the project manager
consider to reduce personal bias and increase buy-in?
For most organizations, which of the following is the MOST efficient method to communicate the project status to a large group of stakeholders?
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:
Which of the following is MOST likely the cause?
Which of the following indicators will assist the project manager in determining the health of the budget?
Which of the following project management tools provides an authoritative source of the project performance guidelines?
Which of the following documents focus primarily on support activities after the completion of a project? (Choose two.)
A new project manager is assigned in the middle of a seven-month project. The project is behind schedule, and there is only historical weekly cost data available.
Which of the following best practices should the project manager perform to assess project costs?
At the end of the fiscal year, the project manager of a well-performing project is notified the project budget may be increased. The project sponsor wants to use an incremental approach to complete more work. Which of the following is the BEST way for the project manager to respond?
The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors?
A project manager wishes to track a project’s performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?