A project has activities on the critical path that must be completed before other activities can start:

Task A is dependent on Task C before Task D can be completed.

Task A requires Task B to start.

Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?

Options:

A.

B, A, D

B.

C, B, D, A

C.

D, A, C

D.

B, C, A, D

Buy Now
Questions 62

A new corporate policy was approved that will positively affect the project.

Which of the following should the project manager do FIRST?

Options:

A.

Schedule the change

B.

Review the communication plan

C.

Update the issue log

D.

Update the risk register

Buy Now
Questions 63

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates

used to create the baseline were based on historical data, which of the following should the project manager

consider as a root cause for potential issues with cost overruns?

Options:

A.

Requirements

B.

Lessons learned

C.

Budget

D.

Environment

Buy Now
Questions 64

Three IT companies have agreed to summarize their efforts as a common organization to generate new businesses in the IT cloud computing industry. Which of the following is the type of organizational change described?

Options:

A.

Expansion

B.

Rightsizing

C.

Merger

D.

Onboarding

Buy Now
Questions 65

Which of the following are the BEST risk analysis tools to determine a project’s risk level? (Select two.)

Options:

A.

Fishbone diagram

B.

RACI matrix

C.

Monte Carlo

D.

Process flowchart

E.

Expert judgment

F.

Project dashboard

Buy Now
Questions 66

Which of the following is used to perform a root cause analysis?

Options:

A.

Ishikawa diagram

B.

Bar chart

C.

Pareto diagram

D.

Scatter plot

Buy Now
Questions 67

A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present.

This review is referred to as:

Options:

A.

change management

B.

A milestone

C.

a tollgate

D.

an incident response

Buy Now
Questions 68

A project team has failed to deliver on changes the project manager outlined on a call two weeks ago. The project team members indicate they did not remember the contents on the call. Which of the following should the project manager do FIRST to improve the level of awareness of changes to the project schedule?

Options:

A.

Define the communications plan.

B.

Record the missed tasks on the issue log.

C.

Provide meeting minutes after each call.

D.

Complete a fishbone diagram.

Buy Now
Questions 69

A project manager has developed the initial schedule for an upcoming project.

PK0-004 Question 69

Using the attached schedule, which of the following is the critical path?

Options:

A.

12 days

B.

14 days

C.

16 days

D.

17 days

Buy Now
Questions 70

A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.

Which of the following is MOST appropriate for the project manager to do NEXT?

Options:

A.

Refer to the contingency plan

B.

Conduct an immediate emergency team meeting

C.

Perform a SWOT analysis

D.

Implement the risk response plan

Buy Now
Questions 71

Which of the following information does the project risk register typically contain?

Options:

A.

Type of risk, identified risk, risk response, impact of risk, severity of risk

B.

Type of risk, project task, risk response, impact of risk, severity of risk

C.

Type of risk, identified risk, risk response, project schedule risk, severity of risk

D.

Type of risk, identified risk, risk response, impact of risk, risk avoidance

Buy Now
Questions 72

An employee is assigned to a project and is developing a project charter. Which of the following are some of

the constraints the employee would typically face at this stage of the project?

Options:

A.

Environment, resources, requirements, and quality

B.

Budget, quality, resources, and schedule

C.

Deliverables, scope, and budget environment

D.

Budget, scope, quality, and schedule

Buy Now
Questions 73

A PM receives notification that an issue will impact a deliverable on the critical path. The issue is logged with a unique ID and assigned to a team member; however, the team member has not addressed it after a week. Which of the following would be the BEST approach to resolving the issue?

Options:

A.

Assign a different team member to resolve the issue before the next status meeting.

B.

Review the issue with the assigned team member to determine a due date.

C.

Set a due date to resolve the issue and inform the assigned team member.

D.

Report the team member to a functional manager for disciplinary action.

Buy Now
Questions 74

Which of the following project phases occurs when requirements are detailed?

Options:

A.

Initiation

B.

Monitor and control

C.

Planning

D.

Closing

Buy Now
Questions 75

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

Options:

A.

Critical Path Method

B.

Critical Chain Method

C.

Arrow Diagramming Method

D.

Gantt Chart Method

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project +
Last Update: Dec 9, 2024
Questions: 796

PDF + Testing Engine

$164.99
$57.75

Testing Engine

$124.99
$43.75

PDF (Q&A)

$104.99
$36.75