Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?
A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.
Which of the following is the BEST risk mitigation strategy that the project manager should use?
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.
Which of the following should the project manager do to resolve this issue?
The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?
A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?
A vendor is unable to deliver an order by the specified date.
Which of the following should be the project manager’s NEXT steps? (Choose two.)
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?
PDF + Testing Engine |
---|
$57.75 |
Testing Engine |
---|
$43.75 |
PDF (Q&A) |
---|
$36.75 |
CompTIA Free Exams |
---|
|