Master the CompTIA PK0-004 Exam: Essential Study Tips and Strategies

Questions 166

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Options:

A.

SOW

B.

PO

C.

SLA

D.

MOU

Buy Now
Questions 167

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

Options:

A.

The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.

B.

The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.

C.

The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.

D.

The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.

Buy Now
Questions 168

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.

Which of the following are critical for the project manager to provide?

Options:

A.

Cost, schedule, organizational chart, and risks/issues

B.

Risks/issues, cost, RACI chart, and action items

C.

Schedule, cost, risks/issues, and milestones

D.

Action items, organizational chart, schedule, and NDA

Buy Now
Questions 169

A project manager has identified a minor skills gap in the operational team that will end up supporting the project solution.

Which of the following is the BEST risk mitigation strategy that the project manager should use?

Options:

A.

Organize adequate training and have one of the operational staff as part of the project team.

B.

Raise a risk in the risk register, identify the likelihood and the consequence of the risk occurring.

C.

Have the project adequately document the solution and ensure a transition is in place.

D.

Escalate this as an issue to the project control board and ensure that there is adequate discussion.

Buy Now
Questions 170

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.

Which of the following should the project manager do to resolve this issue?

Options:

A.

Update the scope management plan.

B.

Modify the project baselines.

C.

Implement change control management.

D.

Inform the stakeholders of the issue.

Buy Now
Questions 171

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

Options:

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Buy Now
Questions 172

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.

Which of the following factors will MOST likely influence the communication methods used in the project?

Options:

A.

Personal preferences

B.

Technological factors

C.

Language barriers

D.

Cultural differences

Buy Now
Questions 173

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.

Which of the following is the FIRST step the project manager should take?

Options:

A.

Assess the risk register’s new items.

B.

Review the task start and finish dates.

C.

Obtain additional resources.

D.

Analyze the assigned hours.

Buy Now
Questions 174

A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management methodology for this requirement?

Options:

A.

Waterfall

B.

Agile

C.

PRINCE2

D.

Bottom-up

Buy Now
Questions 175

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.

Which of the following documents should the project manager create?

Options:

A.

Business case

B.

Project charter

C.

Scope statement

D.

Project management plan

Buy Now
Questions 176

Using Scrum, which of the following are discussed in a daily standup meeting?

Options:

A.

What was done yesterday, what is planned for today, and what roadblocks need to be removed

B.

What was done yesterday, what is planned for the week, and what issues were resolved

C.

What was done yesterday, what is planned for today, and what deliverables were completed

D.

What was done yesterday, what is planned for this week, and what items from the backlog are priority

Buy Now
Questions 177

A vendor is unable to deliver an order by the specified date.

Which of the following should be the project manager’s NEXT steps? (Choose two.)

Options:

A.

The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.

B.

The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.

C.

The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.

D.

The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.

E.

The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.

Buy Now
Questions 178

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Options:

A.

EAC

B.

BAC

C.

TCPI

D.

ETC

Buy Now
Questions 179

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

Options:

A.

follow the change process flow and notify the legal department after the change is implemented.

B.

extend a formal invitation to the legal department representative to join the CCB.

C.

hold a separate meeting with the legal department representative and ask for approval.

D.

notify the legal department representative in the event of an upcoming audit.

Buy Now
Questions 180

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?

Options:

A.

During the planning phase, the project manager should have recognized the relationship between the vendor’s and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.

B.

The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.

C.

During the project team’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.

D.

During the project team’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project +
Last Update: Dec 9, 2024
Questions: 796