Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.
What should program A’s program manager update and review first with the stakeholders?
You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?
A small, regional utility closes a customer rewards program and transitions it to operations. The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?
Which of the following statements are true regarding program scope statement? (Choose three.)
Martha is the program manager for her organization. One of the projects of a program is done but is also considerably over budget. Kay, the project manager, has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Martha instruct Kay to do with the information regarding the schedule delays and cost overruns?
The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively
address the risks.
In this situation, what should the program manager change about the risk management plan?
What project management term would you associated with a predetermined budget you’re your program?
A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?
Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?
A global financial system is being delivered by the program team to allow access from anywhere in the world. Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted to validate compliance with this new regulation. This event, which was not anticipated at this phase of the program, will generate additional work for the program team. This effort is not included in the current program roadmap and benefits delivery plan.
What immediate actions should the program manager take?