A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.
What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?
You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?
You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?
A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program’s benefits sustainment and transition plan. What should the program manager do to create this plan?
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company’s CEO endorses a new program to promote and support this strategy. However, before the program is formally initiated, this strategy must be aligned with the organization’s strategic goals and objectives.
What should the program manager develop first?
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?
Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?
Which of the following represents the duration of activities against a calendar?
The program manager wants to ensure that a program contributes to shareholder value.
The program manager should verify alignment with which of the following?