Questions 81

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:
A.

Forming

B.

Storming

C.

Norming

D.

Performing

PMI CAPM Premium Access
Questions 82

Which of the following are three inputs to the risk register?

Options:
A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Questions 83

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:
A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Questions 84

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:
A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Questions 85

Exhibit A is an example of which of the following types of Sequence Activities?

CAPM Question 85

Options:
A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Questions 86

Which of the following is a group decision-making technique?

Options:
A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Questions 87

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Options:
A.

0.8

B.

0.89

C.

1.13

D.

1.25

Questions 88

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:
A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Questions 89

Which of the following is a tool and technique used to monitor risk?

Options:
A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Questions 90

The diagram below is an example of a:

CAPM Question 90

Options:
A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Questions 91

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:
A.

Two

B.

Four

C.

Five

D.

Twelve

Questions 92

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:
A.

event.

B.

response,

C.

perception.

D.

impact.

Questions 93

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:
A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Questions 94

Which of the following can be used as an input for Define Scope?

Options:
A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Questions 95

Which technique is utilized in the Control Schedule process?

Options:
A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Questions 96

In the basic communication model, which term refers to the method that is used to convey the message?

Options:
A.

Decode

B.

Encode

C.

Medium

D.

Noise

Questions 97

Which of the following is a tool or technique used in the Determine Budget process?

Options:
A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Questions 98

During project selection, which factor is most important?

Options:
A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Questions 99

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:
A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Questions 100

Funding limit reconciliation is a tool and technique used in which process?

Options:
A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget