Achieve Success in the PMI CAPM Exam: A Detailed Certified Associate in Project Management (CAPM) Guide

Questions 61

The project manager needs to review the templates in use. The templates are part of the:

Options:
A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

PMI CAPM Premium Access
Questions 62

Which of the following is an output of Direct and Manage Project Execution?

Options:
A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Questions 63

Co-location is a tool and technique of:

Options:
A.

Develop Human Resource Plan.

B.

Manage Project Team.

C.

Develop Project Team.

D.

Acquire Project Team.

Questions 64

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:
A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Questions 65

Which process should be conducted from the project inception through completion?

Options:
A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Questions 66

In which Project Management Process Group is the project charter developed?

Options:
A.

Monitoring and Controlling

B.

Executing

C.

Initiating

D.

Planning

Questions 67

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:
A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Questions 68

Analogous cost estimating relies on which of the following techniques?

Options:
A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Questions 69

An input to the Manage Project Team process is:

Options:
A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Questions 70

Stakeholder satisfaction should be managed as a key project:

Options:
A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Questions 71

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:
A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Questions 72

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:
A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Questions 73

An input to Conduct Procurements is:

Options:
A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Questions 74

Which of the following Project Communication Management processes uses performance reports as an input?

Options:
A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Questions 75

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

Options:
A.

Cost-reimbursable contracts

B.

Time and Material contracts (T&M)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Questions 76

Which of the following is a tool and technique used in the Develop Schedule process?

Options:
A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Questions 77

Which characteristics do effective project managers possess?

Options:
A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Questions 78

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:
A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Questions 79

Prototype development may be used as a tool for which of the following risk response strategies?

Options:
A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Questions 80

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:
A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.