Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Which piece of information is part of the WBS Dictionary?
Which cost estimate technique includes contingencies to account for cost uncertainty?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
Which can be used to determine whether a process is stable or has predictable performance?
Which of the following is an output of the Distribute Information process?
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Labor, materials, equipment, and supplies are examples of:
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
An input to the Perform Integrated Change Control process is:
Which of the following documents allows the project manager to assess risks that may require near term action?
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
Another name for an Ishikawa diagram is:
The primary benefit of the Plan Schedule Management process is that it:
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
When closing a project or phase, part of the process may require the use of which type of analysis?
One of the tools and techniques of the Manage Project Team process is:
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?