PMI CA0-001 Exam Made Easy: Step-by-Step Preparation Guide

Questions 61

Which tool or technique measures performance of the project as it moves from project initiation through project closure?

Options:
A.

Resource leveling

B.

Parametric measuring

C.

Pareto chart

D.

Earned value

PMI CA0-001 Premium Access
Questions 62

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years the expected worth of the equipment is $2,000. Using straight-line deprecation, what is the amount that can be written off each year?

Options:
A.

$600

B.

$1200

C.

$3000

D.

Zero

Questions 63

Which of the following project document is best suited for tracking costs of resources?

Options:
A.

Work breakdown structure

B.

P'sk breakdown structure

C.

Organizational breakdown structure

D.

Resource breakdown structure

Questions 64

_________ is the international organization that controls the standards for quality.

Options:
A.

ISO

B.

CAPM

C.

PMI

D.

iscn

Questions 65

Which of the following subsidiary plan contains the quality objectives for the project?

Options:
A.

Quality baseline

B.

Quality management plan

C.

Process improvement plan

D.

QA checklist

Questions 66

Which of the following does not provided by scope statement?

Options:
A.

Project justification

B.

Project product

C.

Project manager authority

D.

Project objective

Questions 67

You are creating your WBS and keep decomposing tasks into smaller units. How can you tell when you are done?

Options:
A.

Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and duration.

B.

Keep decomposing work until you reach a predetermined number of hierarchy levels to keep the WBS balanced.

C.

Keep decomposing tasks until you reach an amount of work that can be accomplished in one DAY.

D.

Keep decomposing tasks until you reach an amount of work that can be accomplished in one WEEK.

Questions 68

Project success can be achieved only if:

Options:
A.

There is a clear link between the project deliverables and the business strategy.

B.

The project sponsor leads the initiatives.

C.

The project manager is an expert in managing resources.

D.

Team members like project manager.

Questions 69

Which document formally authorizes a project?

Options:
A.

The project charter

B.

Project scope statement

C.

The P'oject contract

D.

Project closing document

Questions 70

A contract cannot contain _____________.

Options:
A.

Illegal activities

B.

deadline for the completion of the work

C.

Penalties and fines for disclosure of intellectual rights

D.

Al1 of the above

Questions 71

What is the communication channel delta if the members in the communication plan are increased from 5 to 10?

Options:
A.

35

B.

5

C.

15

D.

75

Questions 72

You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory

Options:
A.

Hierarchy of needs

B.

Expectancy theory

C.

Achievement theory

D.

Al1 of the above

Questions 73

ISO Stands for __________.

Options:
A.

International Organization for Standardization

B.

International Standardized Organization

C.

'n Standardized Organization

D.

Indiana Standardized Organization

Questions 74

Which one of the following comes first in the project plan?

Options:
A.

Scope Statement

B.

Quality Plan

C.

WBS

D.

Development Plan

Questions 75

From whom do you need to gain the formal acceptance at project closure?

Options:
A.

The customer

B.

The qualify director

C.

Project management office

D.

Project manager