Information collected on the status of project activities being performed to accomplish the project work is known as what?
In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?
The Monitoring and Controlling process group contains which of the following processes?
Stakeholder analysis identifies what information and relates it to the purpose of the project?
Which quality assurance tool and technique confirms the implementation of approved change requests, corrective actions, defect repairs, and preventive actions?
The project team reviews identified risks and the risk response strategy. For one of the risks, the team realizes that the implementation of the risk response would generate another risk.
This new risk is which of the following types of risk?
Which of the following techniques uses historical information to estimate the activity duration?
Which of the following are outputs of the Monitor and Control Project Work process?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?