New Year Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

PMI CA0-001 Exam Made Easy: Step-by-Step Preparation Guide

Questions 136

A Project Cost Management plan is created as a part of:

Options:
A.

Develop Project Management Plan process

B.

Control Costs process

C.

Determine Budget process

D.

Estimate Costs process

PMI CA0-001 Premium Access
Questions 137

A scope management plan In which of the following scope management processes is the scope management plan prepared?

Options:
A.

Initiation

B.

Collect Requirements

C.

Define Scope

D.

Verify Scope

Questions 138

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

Options:
A.

6

B.

4

C.

6.3

D.

6.1

Questions 139

Which of the following plans is not done during the writing of a project plan?

Options:
A.

Executive Communication

B.

Risk Management

C.

Quality Management

D.

Scope Statement

Questions 140

Information should be communicated to __________.

Options:
A.

Everyone in the communication plan

B.

Everyone on the team

C.

Sponsor

D.

Team 'eacl

Questions 141

Which of the following tools and techniques are commonly used in a Define Scope Process?

Options:
A.

Product analysis

B.

Expert Judgment

C.

Alternative Identification

D.

All of the above

Questions 142

Stakeholder influence is greatest at the ______ of the project.

Options:
A.

Beginning

B.

Closing

C.

Controlling

D.

Executing

Questions 143

Which of the following is not a part of the project cost baseline but is included in the project budget?

Options:
A.

Management Contingency Reserve

B.

Management Overheads

C.

Project Management Planing

D.

Activity Cost Contingency Reserve

Questions 144

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

Options:
A.

Create WBS

B.

Vei*

C.

Value analysis

D.

Control Scope

Questions 145

If a project with a CPI of 1.6, what you tell?

Options:
A.

The project is consuming fewer resources than anticipated

B.

The project is using fewer resources than anticipated.

C.

The project is falling behind.

D.

The project is running ahead of schedule.

Questions 146

Which of the following activity is not performed as part of the direct and manage project execution process?

Options:
A.

Monitor implementation of approved changes

B.

Validate deliverables

C.

Staff, train, and manage the project team

D.

Manage cisks and implement risk responses

Questions 147

Which of the following is a common characteristic of most project life cycle descriptions?

Options:
A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Questions 148

__________ involves using project characteristics in a mathematical model

Options:
A.

Analogous estimating

B.

Life-cycle costing

C.

Parametric modelling

D.

Bottom up estimating

Questions 149

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

Options:
A.

30.0

B.

22.5

C.

25.0

D.

27.5

Questions 150

Which of the following is an output of a Verify Scope process?

Options:
A.

Formal acceptance

B.

WBStemplate

C.

SOW acceptance

D.

Rework

Exam Code: CA0-001
Certification Provider: PMI
Exam Name: Certified Associate in Project Management (CAPM) Certification
Last Update: Jan 20, 2025
Questions: 525