Exin ASF Exam Made Easy: Step-by-Step Preparation Guide

Questions 1

Which Scrum ritual is meant to look back and improve upon the finished Sprint?

Options:
A.

Daily Scrum.

B.

Sprint Retrospective.

C.

Sprint Review.

Exin ASF Premium Access
Questions 2

Who should update the work estimates during the Sprint?

Options:
A.

Only the team members

B.

The Project Manager

C.

The Product Owner

Questions 3

A large product team features six different teams having ten members each, working on a project that involves four high level features.

How many Product Backlogs should the team have?

Options:
A.

1

B.

4

C.

6

Questions 4

What is the objective of the Scrum-of-Scrums meeting?

Options:
A.

To inform management about the progress of the project.

B.

Bring together all team members of all teams.

C.

Coordinate the work of multiple Scrum teams.

D.

Kick-off an international Scrum project.

Questions 5

A team decided to install a large traffic light in the team hall to indicate whether the latest build was healthy (green), failing a few tests (orange) or failing high priority tests (red).

What term can be used to describe the traffic light?

Options:
A.

Information radiator

B.

Osmotic communication

C.

Triangulation

Questions 6

Collaboration is the most important parameter for the success of an Agile team.

What term best describes this type of interaction?

Options:
A.

Distributed team working.

B.

Information radiator sharing.

C.

Osmotic communication.

Questions 7

Why is planning poker an effective estimation technique?

Options:
A.

It generates a lot of useful discussion and gets team buy-in.

B.

It results in lower estimates as team members will estimate individually.

C.

It triggers a more detailed and task oriented break-up of the story.

Questions 8

Who knows most about the progress towards a business objective or a release?

Options:
A.

The Product Owner

B.

The Scrum Master

C.

The team

Questions 9

During the release planning meeting, it is difficult to agree on priorities.

Sales want to implement some new features to catch up with the competitors.

Marketing want to work on a mobile interface that can prove to be a competitive differentiator.

Customer support want better logging and auditing capabilities to improve maintainability.

What should be done to set the priorities?

Options:
A.

Approach Senior Management and ask for priorities.

B.

Survey the existing customers and prioritize according to their views.

C.

The Product Owner will set the priorities.

Questions 10

Which is a statement of value as described in the Agile manifesto?

Options:
A.

We value customer collaboration over responding to changes.

B.

We value project management over individuals and interactions.

C.

We value processes and tools over comprehensive documentation.

D.

We value responding to change to satisfy the customer.