A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

PK0-005 Question 81

Based on the chart, which of the following is the current status of the project?

Options:
A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

CompTIA PK0-005 Premium Access
Questions 82

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

Options:
A.

The project closeout report

B.

A handover to operations

C.

Phase-gate review documentation

D.

A transition plan

Questions 83

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:
A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Questions 84

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

Options:
A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Questions 85

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:
A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Questions 86

Which of the following best describes the reason a waterfall approach would be used for a project?

Options:
A.

The executive team still has no clear requirements for the product.

B.

The executive team is looking to review the product only once after the product is finalized.

C.

The executive team is expecting constant delivery of components.

D.

The executive team wants to reduce the budget for development.

Questions 87

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

PK0-005 Question 87

Which of the following was the initial cause of the issue?

Options:
A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Questions 88

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:
A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Questions 89

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Options:
A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Questions 90

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

Options:
A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.