Questions 71

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:
A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

CompTIA PK0-005 Premium Access
Questions 72

Which of the following is a quality assurance tool?

Options:
A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Questions 73

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:
A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Questions 74

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:
A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Questions 75

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:
A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Questions 76

Which of the following is the main reason for documenting artifacts?

Options:
A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Questions 77

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

Options:
A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Questions 78

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:
A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Questions 79

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:
A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Questions 80

Which of the following should a project manager consult when deciding how to send updates regarding deliverables?

Options:
A.

Dashboard

B.

Status report

C.

Meeting minutes

D.

Communication plan