Weekend Special 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sale65best

Free CompTIA PK0-004 Practice Exam with Questions & Answers | Set: 15

Questions 211

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

Options:
A.

SCRUM retrospective meeting

B.

Sprint planning meeting

C.

Daily standup meeting

D.

Review meeting

CompTIA PK0-004 Premium Access
Questions 212

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

Options:
A.

Zero

B.

One

C.

Two

D.

Three

Questions 213

A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?

Options:
A.

Accept risk

B.

Mitigate risk

C.

Avoid risk

D.

Exploit risk

Questions 214

A project team on a four-year project has a shortage of workspace within an office. Which of the following is the MOST viable solution for the project team while ensuring work hours are not wasted?

Options:
A.

Secure a new facility, permit remote work, and reduce staff.

B.

Reduce staff, implement BYOD, and permit remote work.

C.

Implement BYOD, secure a new facility, and utilize shared workspaces.

D.

Permit remote work, utilize shared workspaces, and implement BYOD.

Questions 215

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority.

Which of the following effects is this MOST likely to have on the project?

Options:
A.

The deliverables and quality will remain the same, but the cost will increase.

B.

The deliverables and quality will remain the same, but the cost will decrease.

C.

The deliverables and cost will remain the same, but the quality will increase.

D.

The cost and quality will remain the same, but the deliverables will increase.

Questions 216

Which of the following defines a group of projects that work together to achieve a common goal?

Options:
A.

Product

B.

Portfolio

C.

Program

D.

Project plan

Questions 217

A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?

Options:
A.

Scope

B.

Time

C.

Quality

D.

Cost

Questions 218

A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?

Options:
A.

Vendors

B.

Key stakeholders

C.

Resources

D.

Project team

E.

Business analysts

Questions 219

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

Options:
A.

Resource loading

B.

Resource leveling

C.

Prioritizing tasks

D.

Allocating resources

Questions 220

A company hires an outside vendor to provide 24/7 support.

Which of the following documents would determine the contractual obligations?

Options:
A.

PO

B.

SLA

C.

LOI

D.

MOU

Questions 221

A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?

Options:
A.

Language barriers

B.

Time zones

C.

Cultural differences

D.

Personal preferences

Questions 222

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.

Which of the following should the project manager do NEXT?

Options:
A.

Gain approval for the changes.

B.

Identify the approval authority.

C.

Implement the changes.

D.

Create an emergency change request.

Questions 223

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

Options:
A.

Add durations.

B.

Add the start and finish dates

C.

Add tasks.

D.

Add resources.

Questions 224

When forming a project team, there are a number of phases.

When a project team is productive and effective this phase is known as which of the following?

Options:
A.

Forming

B.

Norming

C.

Performing

D.

Storming

Questions 225

A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.

Which of the following strategies is the project manager applying?

Options:
A.

Accepting

B.

Mitigating

C.

Avoiding

D.

Transferring